New Machinery Installation schedule
29-09-2016
After a good innings, Laser #8 will be going into retirement next week.
The proposed schedule:
Tuesday 4th October 08-00 hrs end of production at Cirrus Laser
Tuesday 4th October begin dismantling
Thursday 6th / Fri 7th October loaded on truck and goodbye
Weekend 8th 9th October clean area, dust the cobwebs and clean the floor
Tuesday 11th October Trumpf drill floor for new machine holding-down screws
Wednesday 12th - 17th/18th October delivery and installation of new machine Trumpf
Wednesday 19th October recommence full production including new machine
During this period, we will only have Laser #9 and waterjet for cutting. We will run 24 hours and weekends to maintain our service to our customers.