The month of February saw TransXL undertake a project in Germany, which involved removing a 2400mm Davis Standard/Reifenhaser coextrusion line, 1800m wide Kuhne coextrusion line. Gravimetric blenders, granulators and extruders.
Mechanical and electrical disconnection started on the 3rd Feb 2025. Appropriate fork truck was hired in, along with 90 ton Crane for loading. Once disconnected, 14 lorries were loaded over a 2 week period with the last one loaded on the 5th March 2025. A big thank you to Astral Global Logistics who supplied all the standard trailers, Mega trailer and the low loader to take 1 piece that was 3200mm high.
Look out for further post on the arrival of the equipment at TransXL