Sign In
CONTRACT:
Marlborough College, Marlborough - Grade II Listed Building
EQUIPMENT:
Tube & Fittings + Alu Beams + UBIX Roof System
DESIGN BRIEF:
TEMPORARY ROOF: Designed and erected in three phases. To provide drawings and calculations for a temporary roof to weather protect the building, allowing the roof to be replaced.
ACCESS: To provide drawings and calculations for a partly sheeted / partly netted, general purpose access scaffold with a bridged area to one end. Nom. 2.0m bays and 2.0m lifts. Loaded to 2.0kN/m² using tube and fittings with aluminium beams.
For more information on Marlborough College talk to Access Design & Safety Ltd
Enquire Now
More related to Marlborough College
List your company on FindTheNeedle.